Last week, IMI completed a project in Oakwood, Georgia, for our client that manufactures PVC pipe.  We designed, fabricated, and installed a three story mezzanine for an extruder system. Additionally, we completed a total line installation, baler system, and an unloader.

The “penthouse extension” was installed through the roof of the building, using an IMI 50 ton crane. We removed the roof, installed support columns, the mezzanine, and a temporary roof. Upon completion, IMI reinstalled the permanent roof of the building.

The overall  purpose of the project was to prevent rain from getting into the building so they could continuously run operation. IMI once again, tackles the tough projects with ease.